11-01-12 Capacity Curtailment CH-IT
Dear Market Participants,
The LT Allocated Capacity on the CH-IT interconnector has been curtailed due to network security reasons.
For market period 13/01/2012, the Yearly and Monthly Capacity has been reduced by:
5% on hours 19:00 to 20:00 CET
5% on hours 23:00 to 24:00 CET
For market period 14/01/2012, the Yearly and Monthly Capacity has been reduced by:
5% on hours 00:00 to 07:00 CET
5% on hours 23:00 to 24:00 CET
For market period 15/01/2012, the Yearly and Monthly Capacity has been reduced by:
5% on hours 00:00 to 24:00 CET
For market period 16/01/2012, the Yearly and Monthly Capacity has been reduced by:
5% on hours 00:00 to 07:00 CET
5% on hours 08:00 to 20:00 CET
5% on hours 23:00 to 24:00 CET
For market period 17/01/2012, the Yearly and Monthly Capacity has been reduced by:
5% on hours 00:00 to 07:00 CET
5% on hours 08:00 to 20:00 CET
5% on hours 23:00 to 24:00 CET
For market period 18/01/2012, the Yearly and Monthly Capacity has been reduced by:
5% on hours 00:00 to 07:00 CET
5% on hours 08:00 to 19:00 CET
Best Regards,